Back to all projects · Preview data · Henrietta, NY

Installed footage

210 LF

Installed footage across the project production history loaded so far.

Average pace

26.25 ft/hr

Blended production rate for this job.

Documents / forms

1 / 1

Project-linked document records and saved form submissions.

Production entries

1

Saved field logs tied to this job record.

Core job context

active
Project type

Utility work

Work types

Storm drain, Structures

Assumed bedding

6"

Backfill factor

0.9

Hosted preview is using read-only demo data until the production database lane is wired.

Output by work type

1 types

Storm drain

1 entries

210 LF

26.25 ft/hr

Latest field entries

1 loaded

Storm drain

2+00 to 4+10

210 LF
Date

5/16/2026

Crew / hours

4 people · 8 hrs

Feet / hour

26.25

Conditions

Sandy loam

54F, dry, clear

Documents and forms

2 loaded

Traffic Control Permit

Expires in 12 days

permit

5/16/2026

Compaction testing log

Open workflow

Draft saved

5/16/2026