Installed footage

700 LF

Total footage across the currently loaded production history.

Average pace

28 ft/hr

Blended production pace from footage and hours worked.

Estimated excavation

n/a

Aggregate excavation quantity from current production records.

Estimated backfill

n/a

Aggregate backfill quantity from current production records.

Capture production with calculations

Server-backed form
Hosted preview mode is read-only right now. Production entry will be enabled once the hosted database is wired.

Calculated production feed

3 recent

Lake Avenue Sewer Replacement

Sanitary sewer

330 LF
Date

5/16/2026

Station range

10+50 to 13+80

Feet / hour

34.74

Crew / hours

5 people · 9.5 hrs

Excavation

n/a CY

Bedding

n/a CY

Backfill

n/a CY

Conditions

Mixed clay / fill

47F, wet surface, light wind

Jefferson Road Drainage Package

Storm drain

210 LF
Date

5/16/2026

Station range

2+00 to 4+10

Feet / hour

26.25

Crew / hours

4 people · 8 hrs

Excavation

n/a CY

Bedding

n/a CY

Backfill

n/a CY

Conditions

Sandy loam

54F, dry, clear

Townline Watermain Extension

Watermain

160 LF
Date

5/16/2026

Station range

0+00 to 1+60

Feet / hour

21.33

Crew / hours

4 people · 7.5 hrs

Excavation

n/a CY

Bedding

n/a CY

Backfill

n/a CY

Conditions

Road base / stone

51F, overcast

Production by job

3 projects

Lake Avenue Sewer Replacement

1 entries · avg crew 5

330 LF

34.74 ft/hr

Jefferson Road Drainage Package

1 entries · avg crew 4

210 LF

26.25 ft/hr

Townline Watermain Extension

1 entries · avg crew 4

160 LF

21.33 ft/hr

Production mix

3 work types

Sanitary sewer

1 entries

330 LF

34.74 ft/hr

Storm drain

1 entries

210 LF

26.25 ft/hr

Watermain

1 entries

160 LF

21.33 ft/hr